1.Airway system: The oil, water separator and the tank can be drained daily and the oil
atomizer should have enough oil.
2. Water system: Water valve should be switched well, ruling out in time if the fault comes out.
3.The transmission system: V-belt tension, chain tightness, coupling interval, conveyor belt is normal.
4.Mixing system: Mixing blades, door panels, liners, agitator arms are missing and damaged.Cleaning up the
materials if they are remaining in concrete mixer in any time.
5.Lubrication system: Each grease mouth is full of grease, which is the focus of the shaft seal.Checking the
height of each tank, filled with grease.